July 7, 2019
​
Five months ago we started this journey. And last night we finally were able to celebrate with our family, friends, colleagues, and neighbors!

Last big step - finishing our mural! Good progress already made this week!



June 30, 2019
​
So much progress in the last 10 days!
Exterior painted, new ADA-compliant entrance ramp completed, stage floor finished, seating installed, stage curtains installed! AND CERTIFICATE OF OCCUPANCY APPROVED! We are in the home stretch!





June 19, 2019


Exterior work starting with parking lot repair, striping, and tuck pointing the walls
where the mural will be painted!
And interior work focused on constructing our stage floor!
Vapor barriers, multiple levels of flooring, and first coats of paint.




June 9, 2019
​
We're not quite done - but we're getting there!



Cabaret Space Rehearsal Room Studio Rehearsal



Green Room Dressing Room Dressing Room



Practice Room Restroom Restroom


Performers Hall to Stage Main Stage
June 3, 2019
​
A lot has been going on since we last posted!
We got our temporary certificate of occupancy and actually held auditions in the space this weekend!
Rehearsal Rooms are done, Cabaret Space is done, Dressing Room and Green Room are done, Bathrooms are done. We have a sprinkler system, a fire alarm system, a security alarm system and a very fancy keying system and internet service.
There is still more work to do to complete the main stage area, but it's coming along!


May 2, 2019
​
Interior painting done, cabaret space ready for flooring and some beautiful bathroom tile!



April 26, 2019
​
We have a pipe grid! And the painting in the rest of the space is coming along nicely!


April 14, 2019
​
We have paint in the Main Stage and Backstage area!



April 11, 2019
​
The cabaret space and the two conference rooms -- looking good!



March 23, 2019
​
We have seating platforms, door frames, and duct work going in!



March 19, 2019
​
Seating platforms going into the main stage ~ More walls going up in the
cabaret space and the Studio rehearsal room!



Outside walls insulated - and sheet rock going up!
March 9, 2019
​
This is inside the Main Stage theater - from the back stage
looking toward where the audience seating will be located.
See the control room?

More Walls!
March 4, 2019

Some walls coming down, and others going up!
February 28, 2019




"Before"
February 7, 2019
9,000 Square Feet of Open Space